Gantry Shear Power Supply: Transformer Sizing From 200 to 2000 Tons

Size the transformer from the motor package, not from the shearing force. HUAXIN’s rule for the minimum dedicated supply is kVA = (motor kW + 5) ÷ 0.8, rounded up. Across our hydraulic gantry shear range that runs from 34 kVA for a single 22 kW motor on the 200 t class to 694 kVA for 10×55 kW on the 2,000 t class. This guide sets out the gantry shear power supply for every model, plus starting, generator and voltage choices.

Our electrical team in Tangshan wires each cabinet to the customer’s supply before the factory load test. Figures here are the ones we check against site data at quotation.

The Sizing Rule, Worked Through

Two parts. The 5 kW on top of the motor rating is an allowance for the control circuit and auxiliary loads. Dividing by 0.8 converts real power in kW to apparent power in kVA at a typical motor power factor.

Take a 500 t shear with 2×45 kW. Motor total is 90 kW. Add 5 to get 95, divide by 0.8 to get 118.75, and round up to 119 kVA. That is the smallest transformer capacity that should be free for the shear alone.

The rule gives a floor. It is not a recommendation to buy a transformer at exactly that rating if the yard plans to add a baler, a crane or a second shear later.

Gantry Shear Power Supply by Model

Motor options below are the standard packages for each class. Pick the row that matches the package on your quotation.

Shear class Motor option Total motor kW Minimum transformer kVA Starting
200 t (2,000 kN) 22 kW 22 34 Single starter
30 kW 30 44 Single starter
2×22 kW 44 62 Sequential start
315 t (3,150 kN) 37 kW 37 53 Single starter
45 kW 45 63 Single starter
2×22 kW 44 62 Sequential start
400 t (4,000 kN) 45 kW 45 63 Single starter
2×37 kW 74 99 Sequential start
2×45 kW 90 119 Sequential start
500 t (5,000 kN) 2×37 kW 74 99 Sequential start
2×45 kW 90 119 Sequential start
630 t (6,300 kN) 2×45 kW 90 119 Sequential start
3×45 kW 135 175 Sequential start
1,000 t (10,000 kN) 3×45 kW 135 175 Sequential start
4×45 kW 180 232 Sequential start
1,250 t (12,500 kN) 4×45 kW 180 232 Sequential start
5×45 kW 225 288 Sequential start
6×45 kW 270 344 Sequential start
1,600 t (16,000 kN) 6×55 kW 330 419 Sequential start
8×55 kW 440 557 Sequential start
2,000 t (20,000 kN) 8×55 kW 440 557 Sequential start
10×55 kW 550 694 Sequential start

Notice the overlaps. A 400 t and a 630 t machine can need the same 119 kVA, because both can run 2×45 kW. The force difference comes from cylinder size and frame, not from extra motor power. Output differs, though: 3.5–5.5 t/h against 6.0–8.0 t/h.

Small yards often start with a 200 ton gantry shear on an existing supply. Mill-side lines built around a 2000 ton gantry shear are a substation conversation from day one, because 557 or 694 kVA of dedicated capacity is rarely sitting unused on an existing plant feeder.

Choosing a Motor Package Around a Tight Supply

On a tight supply, the motor option is the lever. Three typical situations from our quotation work:

  • A 200 t yard with little spare capacity. The single 22 kW package needs 34 kVA, against 62 kVA for 2×22 kW. Output sits lower in the 2.0–4.5 t/h band, but the machine runs without a transformer upgrade.
  • A 400 t yard planning growth. The single 45 kW motor needs 63 kVA. Moving to 2×45 kW lifts the requirement to 119 kVA and pushes output toward 5.5 t/h.
  • A 1,250 t mill line. Going from 4×45 to 6×45 kW adds 112 kVA to the minimum, from 232 to 344 kVA. That is often the difference between using the existing substation and ordering a new one.

In each case the gantry shear power supply, not the cutting job, set the package. Agree it early.

A Shared Transformer Changes the Sum

The table assumes the transformer feeds the shear only. Few yards work that way, because the shear is usually added to a site that already runs a crane, a workshop and offices from one incoming line. Cranes, a baler, workshop welders, lighting and offices share the same supply.

Add their running loads to the shear figure, then check the result against the transformer nameplate with your electrician. Spare capacity is what remains on your busiest day, with the crane lifting, the baler cycling and the welders running, not the figure printed on the nameplate. A yard that ignores this finds out during the first heavy cut, when voltage sags and contactors drop out.

Staged Starting on Multi-Motor Machines

Starting is harder on a supply than running. A motor draws several times its rated current for the first seconds after switch-on, while the windings magnetise and the pump comes up to speed. On a 10×55 kW package, starting everything at once would hit the transformer with a surge it was never sized for.

So multi-motor machines start in sequence. The PLC brings each motor-pump group online one after another, through star-delta or soft-starter modules, and waits for each group to settle before calling the next one. Each step adds one motor’s surge to an already running load. That keeps voltage dips off the plant transformer, which matters when the shear shares a supply with cranes or mill equipment.

Single-motor machines in the 200 t to 400 t classes use a starter matched to your supply. The choice is agreed in writing before the build. For a deeper look at the starter types at heavy tonnage, read starting methods at mill scale.

Generator and Diesel Drive

Every class can be ordered for grid electric, generator or diesel drive, and the last two suit remote yards, seasonal sites and demolition projects that have no grid connection at all.

A generator set reacts to starting surges more sharply than a grid transformer of the same rating. Its rating therefore needs headroom above the kVA figures in the table, which we confirm against the generator’s data sheet. Staged starting helps here too.

A direct diesel drive avoids electrical starting surges entirely, at the cost of a different power train and fuel handling. Our comparison of diesel vs electric scrap machines covers running cost and upkeep.

Voltage and Frequency Options

We build for 230 V, 380 V, 400 V, 415 V, 440 V or 480 V, at 50 Hz or 60 Hz. The cabinet, motors and starters are built for one combination. A machine built for 380 V 50 Hz is not adapted on site to 480 V 60 Hz; it is a different electrical build.

That is why the voltage and frequency line on the order deserves a second check by your own electrician, against the actual switchboard rather than a figure copied from an old invoice. A wrong figure found at the port costs weeks.

What to Send HUAXIN Before the Build

  1. Supply voltage and frequency at the point of connection.
  2. Transformer rating in kVA and the loads already on it.
  3. Distance from the transformer to the shear, for cable sizing by your electrician.
  4. Grid, generator or diesel, with the generator’s data sheet if relevant.
  5. Climate: ambient temperature range and dust, which affect cooling and cabinet build.
  6. Your preferred motor package, or your target t/h so we can recommend one.

The general motor discussion for a single class is in motor kW and your site supply. All nine classes and their motor options are listed in the hydraulic gantry shear category.

Power Supply FAQ

Is the kVA in the table the transformer I should buy?

It is the minimum free capacity for the shear alone. Add other loads on the same supply and leave room for future machines.

Can the motor package be changed after delivery?

Not practically. Motors, pumps, starters and cabinet are matched at the build, so fix the package at quotation.

Does more motor power mean more cutting force?

No. Force comes from the cylinders and frame. More pump groups shorten the cycle and move output toward the top of the t/h band.

Can a 1000 t shear run on a generator?

Yes. Generator and diesel drive are available for every class. We size the generator with you against the 175 or 232 kVA minimum for its motor package, plus starting headroom.

Send your voltage, frequency, transformer rating and scrap mix through our contact page. You will receive a written quotation with the electrical scope confirmed within 48 hours.